Helotes Creek Gravity Main Project

Posted in News

The Helotes Creek Gravity Main and Lift Station #246 Elimination Project by San Antonio Water System (SAWS) is underway. The project is part of the work required by the Environmental Protection Agency (EPA) consent decree to address sewer infrastructure across the SAWS service area. The project consists of approximately 14,700 feet of 6-inch to 18-inch new sewer main along State Highway 16, Old Bandera Road, Riggs Road, and F.M. 1560.

Construction is expected to be completed by December 2024, weather permitting. Construction is being carried out by an independent contractor, however, SAWS inspectors regularly visit the site to ensure progress and compliance with all regulations and codes. During construction, the operation of heavy trucks in the vicinity will increase and traffic may be impacted on State Highway 16, Old Bandera Road, Riggs Road, and F.M. 1560.

Construction Timeline on Old Bandera Road (Old Town Helotes area)

🚧 View Phase Map – Trench repair with asphalt will be completed before moving to the next phase

Bypass Setup
📅 Dates: 9/18/2023 to 10/1/2023

Phase 1 – Closure from 14769 Old Bandera Road to Antonio Drive
📅 Dates: 10/2/2023 to 10/15/2023
📍Limits: South of closure access: Old Bandera Rd / North of closure access: Dent Ln, Antonio Dr via 1560

Phase 2 – Closure at Antonio Drive Intersection
📅 Dates: 10/16/2023 to 10/22/2023
📍Limits: South of closure access: Old Bandera Rd, Scenic Loop Rd, Antonio Dr via 1560 / North of Closure Access: Dent Ln

Phase 3 – Closure from Antonio Drive Trenchless Construction
📅 Date: 10/17/2023 to 11/7/2023
📍Limits: South of closure access: Old Bandera Rd, Scenic Loop Rd, Antonio Dr via 1560 / North of closure access: Dent Ln

Resources

View the SAWS Helotes Creek Gravity Main Project presentation.

Questions regarding this SAWS project? Contact Cecilia Picazo at 210-233-3750 or by email at Cecilia.Picazo@saws.org